Abstract:
POWERGRID, a state-owned power transmission company in India, is seeking a partner to participate in its tariff bid for a 187.5 MW/750 MWh Battery Energy Storage System (BESS) at the Maheswaram 400/220 kV substation of TGTRANSCO in Telangana. The project is being procured by TGGENCO through a Request for Selection (RfS) and will receive Viability Gap Funding (VGF) support through the Power System Development Fund (PSDF). Under Package TS-BESS-01, the partner will be selected through a competitive bidding process, with bids due on 19 October 2026. The lowest evaluated bidder will be shortlisted and required to sign an exclusive Memorandum of Understanding (MoU) with POWERGRID before submission of the tariff bid. If POWERGRID secures the project, the selected partner will be responsible for building the four-hour BESS within 15 months and operating and maintaining it for 15 years.